Significant defects in CJIA expansion – Public Works Minister

1

Minister of Public Works Juan Edghill says the current state of the Cheddi Jagan International Airport (CJIA) Modernisation Programme leaves much to be desired and the new PPP/C Government will have to work to restore the project.

The project, which was initiated by the Donald Ramotar (2011-2015) administration, was taken over by the former APNU+AFC Coalition Government, however, after five years in office, Minister Edghill said the programme remains a catastrophe.

He said what was designed, signed and expected to be delivered, was not what Guyanese received.

During a virtual press conference Wednesday, the Minister said the “reformulated, remodelled, downsized and renovated programme is troublesome.

“The expected new airport with new terminal buildings, eight-passenger air bridges and the capacity for eight aircraft at one time, has not yet been realised.

“The runway is incomplete; works are ongoing at both ends. The terminal building that was renovated has significant defects. Leaking roofs, improper tiling, problems with air conditioning, lighting and the list of woes continues.”

An April 2018 photo of works at the CJIA

Of greater interest, he noted, is the fact that both incoming and outgoing passengers, still have to walk on the tarmac, as the four newly installed air bridges have malfunctioned.

The Minister recalled that the original design by the PPP/C catered for eight air bridges but this was not done. The last administration went to Parliament for supplemental provision to purchase two air bridges in addition to the two that the contractor had installed.

“This project is also very troubled. The brief from the project engineer has indicated that there is an effort being made to get the contractor to comply with the terms and conditions of the contract and to deliver what was signed on to. It is not happening,” Minister Edghill stated.

He noted that the contract for the completion of the airport, even in its extended version, expired at the end of December 2018. Two years later, there is no significant work being done by the contractor to comply and complete this project.

Therefore, the ministry will very shortly be engaging the contractor on the way forward.

Minister Edghill assured that the PPP/C Government is committed to the modernisation of the CJIA. He further assured that every effort is being made to ensure that the contractor complies, to produce a product that can benefit Guyanese. (Extracted and modified from DPI)

Advertisement
_____
1 Comment
  1. Xhrp2wkb1 says

    Tsk Tsk. PNC was in charge so no one is surprised.

Leave A Reply

Your email address will not be published.